EXPRESSWAYS
To ease transport flow in GKMA, the Government has embarked on developing expressways. Towards this, Kampala-Entebbe Expressway was completed in 2018 and the Kampala-Northern Bypass capacity improvement is expected to be completed in 2021. Over the next five years the following expressways will be constructed.
TABLE 20: EXPRESSWAYS PLANNED | ||
NO | EXPRESSWAY | STATUS |
1 | Busega-Mpigi | Work commenced in 2019 |
2 | Kampala Flyover Project | Construction work ongoing |
3 | Kibuye-Busega | Construction work Completed |
4 | Kampala-Jinja | Under Procurement |
5 | Kampala Southern Bypass | Works to commenced |
6 | Kampala-Bombo | Design completed |
7 | Nakasero-Northern Bypass | Design completed |
8 | Kampala Outer Beltway/Ring Road | Design completed |
9 | Kampala-Busunju-Hoima | Design ongoing |